N Dade 85 over West Prong Sons Creek
8:15am- crew laying out pile locations.
Bent 2 work pad formed up.
8:56am- pile driving begins on Bent 1.
9:13am- 2nd pile going in.
9:25am- 3rd pile getting set.
9:44am- 4th pile going in. This hole when pre-bored never encountered rock. At 20’ the drilled hit a cavern.
9:57am- 4th pile in for now. A 40’ piece of pile will be here tomorrow and get welded on; pile will be driven then to see if it will hit refusal.
First three pile were driven to refusal. Contractor to notify us on driving 4th hole tomorrow.
10:42am- update: pile and welder will be here this afternoon and pile will be driven on 4th hole today yet.
10:45am- cutoffs are now occurring.
10:42am- update: pile and welder will be here this afternoon and pile will be driven on 4th hole today yet.
10:45am- cutoffs are now occurring.
12:43pm- the extra 40’ pile just got unloaded.
1:30pm- section is getting welded up to pile in the ground now.
2:31pm- still welding up pile as work pad is getting aet up here on Bent 1 now.
3:29pm- 4th hole now has pile to refusal. Of the 40’ piece welded on today; the cutoff is 17’-10&3/4”.
3:50pm- Summary of pile driving: