N Dade 85 over West Prong Sons Creek
Arrived onsite at 07:40am- no drill rig here for pre bore. Labor interview done.
9:45am- drill rig now onsite.
Heat numbers as seen on pile:
9:55am- drill rig fires up to begin drilling on Bent 2.
Measurements on offsets are checked for center of bit.
10:12am-Drilling is now underway.

11:24am- checking grade on hole. Still more to go…
11:24am- checking grade on hole. Still more to go…
1:20pm- Finally to grade. Hole will be cleaned up and filled with belt millings.
1:45pm- 2nd hole now started.
3:55pm- grade check here on 2nd hole; another foot or so to go…
4:28pm- 2nd hole now to depth. Backfill this to move onto #3.
5:05pm- 3rd hole is underway as I will be leaving site now. Hole will not get finished tonight. Crew says they will resume tomorrow.