N Dade 85 over West Prong Sons Creek


Arrived onsite at 07:40am- no drill rig here for pre bore. Labor interview done. 
9:45am- drill rig now onsite. 

Heat numbers as seen on pile:











9:55am- drill rig fires up to begin drilling on Bent 2. 

Measurements on offsets are checked for center of bit. 
10:12am-Drilling is now underway. 

11:24am- checking grade on hole. Still more to go…

1:20pm- Finally to grade. Hole will be cleaned up and filled with belt millings. 





1:45pm- 2nd hole now started. 

3:55pm- grade check here on 2nd hole; another foot or so to go…

4:28pm- 2nd hole now to depth. Backfill this to move onto #3. 





5:05pm- 3rd hole is underway as I will be leaving site now. Hole will not get finished tonight. Crew says they will resume tomorrow. 