Concrete arrived at 9:00 testing 5.5 AIR 4 SLUMP 60 deg and made 3 cylinders 9:46 continue to place conch for bent 2 Stripped forms from bent 1 and setting erosion control on project
8:35am Prepping site for trucks with NU Girders 9:00am NU Girders have arrived on site 9:20am Unloading the first NU Girder 9:35am NU Girder 3 set 10:00 NU Girder 2 set 10:30am last NU Girder set
Arrived onsite at 07:40am- no drill rig here for pre bore. Labor interview done. 9:45am- drill rig now onsite. Heat numbers as seen on pile: 9:55am- drill rig fires up to begin drilling on Bent 2. Measurements on offsets are checked for center of bit. 10:12am-Drilling is now underway. 11:24am- checking grade on hole. Still more to go… 1:20pm- Finally to grade. Hole will be cleaned up and filled with belt millings. 1:45pm- 2nd hole now started. 3:55pm- grade check here on 2nd hole; another foot or so to go… 4:28pm- 2nd hole now to depth. Backfill this to move onto #3. 5:05pm- 3rd hole is underway as I will be leaving site now. Hole will not get finished tonight. Crew says they will resume tomorrow.
Comments
Post a Comment