N Dade 85 Bridge over West Prong Creek

Image
  Contractor started placing material on roadway, Contractor will place rock on the south end to allow drainage before placing material on roadway. North End looking south. First lift Started Filling on South end as well, Placed rock first Contractor started digging for side slopes and does not think plan guardrail will work due to no rock face to connect too. Meet with guardrail company to discuss.

N Dade 85 over West Prong Creek

Image
  Site visit to pick up cylinders from Deck pour, contractor will seal deck today and start compaction on Monday.

N Dade 85 over West Prong Creek

Image
7:02am Bridge machine set waiting on concrete. Clearing deck of debris from overnight wind

N Dade 85 over West Prong Sons Creek

Image
Checked machine for proper clearance over deck. All appears good. Slight rise at Bent 2 allowing for hrade onto bridge. 

N Dade 85 over West Prong Sons Creek

Image
Labor board inspection done along with labor interview and erosion control. 

N Dade 85 Over West Prong Sons Creek

Image
8:35am Prepping site for trucks with NU Girders 9:00am NU Girders have arrived on site 9:20am Unloading the first NU Girder 9:35am NU Girder 3 set 10:00 NU Girder 2 set 10:30am last NU Girder set