8:35am Prepping site for trucks with NU Girders 9:00am NU Girders have arrived on site 9:20am Unloading the first NU Girder 9:35am NU Girder 3 set 10:00 NU Girder 2 set 10:30am last NU Girder set
Concrete arrived at 9:00 testing 5.5 AIR 4 SLUMP 60 deg and made 3 cylinders 9:46 continue to place conch for bent 2 Stripped forms from bent 1 and setting erosion control on project
11:49 Waiting on concrete to show 12:29 getting prepped, still waiting on concrete 2:05 Concrete finally showed AIR 6.5 slump 4.5 concrete 72 deg 4 cylinders 2:48 Continue to pour concrete for bent 1 4:25 Start to place concrete from the last truck for the day 4:30 concrete pour completed. Will return tomorrow for the other bent